A commercial and industrial battery tender looks like a pricing exercise. It is not. By the time the technical envelopes are opened, half the bidders are already out: their single-line diagram does not match the site, their load profile is a guess, or their delivery terms assume a port the buyer never mentioned. The list below is the order in which we ask for information, because it is also the order in which evaluation usually happens.
1. Start from the load, not from the cabinet
Every C&I storage quotation collapses into two numbers: how much power the site needs at once (kW), and how long it needs to hold that power (kWh). Buyers often send the second without the first, or send a target capacity copied from a competitor's proposal. Ask instead for:
- Peak demand in kW, and whether it is measured or estimated.
- The load curve — ideally 15-minute interval data for a week, or the highest and lowest day of the month.
- What the battery is for: peak shaving, demand-charge reduction, backup, solar self-consumption, or several at once. The mix changes the cabinet count more than the capacity target does.
With those three, the cabinet size falls out of arithmetic instead of negotiation. A 50 kW site that needs four hours of backup is roughly 200 kWh, which means parallel cabinets rather than one larger unit.
2. Site data that decides the layout
The cabinet is one part of the installation. Tender documents should state the ambient temperature range, whether the room is ventilated, the available footprint and door clearance, the floor loading, and the distance from the cabinet to the distribution board. Two details regularly change a proposal late: ambient temperature above the cabinet's rating (which pushes a site from air cooling to liquid cooling) and a room too narrow for front service access.
3. Electrical interface and protection
Ask for the single-line diagram, the transformer rating, the grid connection voltage and the protection scheme already installed. A C&I cabinet is not a standalone appliance: it has to sit behind protection that was designed for the site, and the interface point has to be written down. Where the buyer has a one-line diagram, we mark the proposed point of connection on it and return it with the quotation — it removes an entire round of questions.
4. The capacity ladder, in published numbers
These are the ratings we publish for the cabinets and containers, so a tender can be compared line by line without waiting for a datasheet pack:
| Model | Power / capacity | Cooling | Enclosure |
|---|---|---|---|
| EAP-CI-50 | 50 kW / 50 kWh | Air | IP54 |
| EAP-CI-112 | 50 kW / 112.53 kWh | Air | IP54 |
| EAP-CI-241 | 125 kW / 241.15 kWh | Air | IP54 |
| EAP-CI-261 | 125 kW / 261 kWh | Liquid | IP54 |
| EAP-CT-1200 | 500 kW / 1.2 MWh (20ft) | Container | ISO container |
| EAP-CT-2400 | 1 MW / 2.4 MWh (40ft) | Container | ISO container |
Cabinets parallel to reach MW scale; above that the container line takes over. The practical ceiling is usually the site transformer and the footprint, not the product.
5. Delivery terms decide the landed comparison
A price without a trade term is not a price. Tender documents should fix the Incoterm, the port or site, who clears import, who pays for inland transport, and whether commissioning is in scope. Two bids that look 15% apart are often the same number once EXW, CIF and delivered-to-site are put on one line. Write the term into the enquiry, not into the clarification round.
6. Documents to request before award
- Datasheet for the exact model being offered, not the series.
- Dimensioned drawing and weight, for floor loading and transport.
- Single-line diagram of the cabinet internals and the interface point.
- Battery and cabinet documentation pack (declarations, transport documents) — ask which items ship with the goods and which are issued on request.
- Warranty terms in writing: what is covered, for how long, and what voids it.
If a supplier answers any of these with “standard” or “available on request”, ask for the file. A tender committee will ask for it too, later and less politely.
7. What to put in the enquiry
A one-page enquiry that gets a usable answer contains: site country and city, peak kW and target kWh, duty description, ambient range, indoor or outdoor, connection voltage, required delivery term and port, target award date, and whether commissioning is required. Add the single-line diagram if one exists. That is enough to size a cabinet, price a container and quote a delivery window without a second round.
Frequently asked questions
Do you quote from a tender document as-is?
Yes, if the document states capacity and delivery terms. Where it only states a target kWh, we reply with the compliant option plus the next size up, so the committee can see the cost of the step.
Can a tender specify a brand of cell or inverter?
It can, and many do. Tell us the requirement at enquiry stage rather than at clarification stage — it changes what can be offered and what the delivery window looks like.
What is the usual scope split on a C&I cabinet?
Cabinet, internal BMS/EMS and factory testing are ours. Civils, the interface protection, cabling to the point of connection and site commissioning are normally the buyer's or the EPC's — write the split into the tender so bids are comparable.
If you are preparing a tender, send the load data and the site conditions to our project desk and we will return a configuration, the datasheet for the exact model and a delivery window. Product references: EAP-CI-241 cabinet and EAP-CT-1200 container. For anything else, contact the project team.